Project Details

 

Project Developer (Proponent)
Project Name: Zafarana 140 MW Wind Power Plant
Organization Name: New and Renewable Energy Authority (NREA)
Organizational Category: Governmental
Organization Address: Dr. Ibrahim Abou El-Naga St., Hay El-Zohor, Nasr City, Cairo
Contact Person: Eng. Samir M. Hassan, Executive Chairman
Phone: + 202 - 2713176
Fax: + 202 - 2717173
Email: nre@idsc.net.eg
Website:  
 

Type of Project

Project Category: Renewable Energy
GHGs: Carbon Dioxide
 

Certified Emission Reductions (CERs)

Crediting Period:

3x7 years

First Year of Crediting Period:

2007

Annual CERs Expected:

290000
 

Project Description

Brief Description of project: • The zafarana wind power plant project is a project located in the Arab Republic of Egypt. • The wind plant consists of 4 clusters: 1. 30 MW wind cluster in cooperation with DANIDA of Denmark which started operation in 2000. 2. 33 MW wind cluster in cooperation with KFW of Germany, which started operation in 2001 as phaseI. 3. 30 MW wind cluster in cooperation with DANIDA, which started operation in 2003. 4. 47 MW wind cluster in cooperation with KFW, which started operation in 2004. • The project generated 515,740 MWh of electricity in 2005. • The yearly CO2 abatement in 2005 reached about 290,000 tCO2e. Brief description of technology: The project implemented proven and reliable technology with technical specification as follows: • Clusters 1 & 2 utilizes Nordex wind turbines type N43 3 bladed having, 600 KW rated capacity, 43 meter diameter, 40 m hub height, stall – regulated. • Clusters 3 & 4 utilizes Vestas wind turbines type V47 3 bladed, 660 KW rated capacity, 47 meters diameter, 45 meters hub height & pitch – regulated..

 

Project Location

Governorate:

Suez

City:

Zaafarana
 

Project Schedule & Cost

Project Start Date: 2007
Project Cost: Million L.E. 883
 

Baseline

Baseline:

Title of the baseline: ACM0002: Consolidated Baseline Methodology for Grid – Connected Electricity Generation from Renewable Energy Sources
 

Project Current Status

PIN: Available
PDD:  
DNA Approval: Letter of no objection
Validation: Not yet
Financing:  
Implementation: Running successfully

 

 

 

 

 
رمز نقطي

Home

رمز نقطي

Events & Workshops

رمز نقطي

Publications

رمز نقطي

CDM Project Portfolio

رمز نقطي

Project Approval Procedure

رمز نقطي

Questions & Answers

رمز نقطي

CDM National Strategy

رمز نقطي

Projects Ideas

رمز نقطي

Projects Database

 

 

 

Copyright © 2004 www.cdmegypt.org All Rights Reserved - Last updated: Tuesday, 25 July 2006